UPGRADE 20 MW GE Unit control System
The project related to the change of a power plant control system. The whole design, implementation and installation phases of this project took four months. Working under time constraints become a routine at HANI ENERGY company due to the limited possibility of power plants in outphasing of their units.
Project: Design and installation of control and protection system for gas turbine
Unit name: GE
Used Technology: DCS SIEMENS PCS7
Estimated time: 4 Month
Unit capacity: 20 Mega Watt
Delivery Date: 2018